GOT HERE Array ( [strictly_necessary] => Array ( ) [functional] => Array ( ) [performance_analytics] => Array ( [0] => Array ( [0] => Kuzsu [1] => [2] => ) ) [advertisement_targeting] => Array ( ) ) Understanding Steel Sheet Piling Temporary Works | Installation & Extraction Methods Skip to content

Scroll to continue

caret-left Back to Latest News

Using Sheet Piling in Temporary Works 21 September 2026

Understanding Steel Sheet Piling Temporary Works

Temporary works in steel piling refer to sheet pile retaining walls that provide structural support for short to medium-term applications, with the intention of removal once their purpose has been served. These structures are crucial in construction projects where temporary earth retention or water exclusion is required.

Unlike concrete, steel piles offer comparatively significant sustainability benefits, as they can be fully recycled. This can be achieved either through direct reuse on another project or by melting down the steel and reforming it into new beams or piles, making them an environmentally responsible choice.

Applications of Steel Sheet Piling Temporary Works

One of the most common examples of temporary works is a steel sheet piled cofferdam. This method is widely used in construction projects where a dry and stable work environment is required below ground level. The process involves:

  1. Sheet pile installation – Steel sheet piles can be either driven or pressed into the ground to create a secure barrier; the installation technique is determined by a variety of factors, including ground conditions, location and environmental constraints.
  2. Excavation – The enclosed area is internally excavated to allow for the construction of underground structures or other necessary works.
  3. Completion and backfilling – Once the required construction is completed, the area is backfilled up to ground level.
  4. Pile extraction – The sheet piles are removed, making way for the final project stage without leaving permanent structures behind.

Temporary Sheet Pile Extraction Methods

The removal of temporary sheet piles, known as extraction or ‘pulling,’ can be carried out using a choice of techniques:

Silent Extraction – The Giken Silent Piler offers vibration-free removal, making it ideal for sensitive locations such as towns and city centres, schools, and hospitals, where noise and ground disturbance must be minimised.

Vibratory Extraction – Using a vibratory attachment fitted to a leader rig or a Movax excavator, piles are loosened and efficiently withdrawn.

Sheet Pile Extraction - Temporary Works
Extraction of sheet piles using vibration, following temporary works to bridge structure on River Nene, Peterborough

Why Choose Steel Sheet Piling for Temporary Works?

Why Choose Ivor King?

Ivor King has over 50 years of experience in steel sheet piling, we specialise in providing innovative and bespoke piling solutions.

Take a look at the range of Steel Piling Solutions we can design and install, and get in touch with our knowledgeable and friendly team to discuss how we can help. Whatever your piling project, we’re your people.

sheet piling solutions

Got a question? Talk to the Sheet Piling experts

Call 024 7639 7272 to speak to one of our team directly or use the button below for our online contact form.

Sheet Piles

Our knowledgeable and experienced team is here to help develop the most feasible and cost-effective solutions for your scheme, and can answer any sheet piling related questions you might have.

What are temporary works in construction? caret-down

Temporary (or enabling) works are structures or systems used to support, protect or enable construction activities during a project. In piling, this can include temporary sheet pile retaining walls, cofferdams, bracing systems and other forms of excavation support. They are generally designed to remain in place only for as long as they are required before being removed or replaced by the permanent works.

What are temporary sheet piles used for? caret-down

Temporary sheet piles are commonly used to provide earth retention and water exclusion during construction, forming a controlled environment for construction to happen below ground level. Applications include supporting deep excavations, forming cofferdams, protecting existing structures and providing temporary retaining walls. Once the permanent works are complete, sheet piles can be extracted and potentially reused.

Do temporary sheet pile walls need additional support? caret-down

Not necessarily. The required support depends on factors including excavation depth, ground conditions, water levels and loading behind the wall. Depending on the design, temporary sheet pile walls may be self-supporting or may require waling beams or internal bracing systems.

Can temporary sheet piles be removed after construction? caret-down

Yes. One of the key advantages of using steel sheet piles for temporary works is that they can be extracted once they are no longer required. Extraction can be carried out using vibratory equipment or silent, vibration-free systems such as GIKEN technology, depending on the site conditions and environmental constraints.

Can temporary sheet piles be reused? caret-down

Yes. Provided the piles remain in suitable condition following extraction, they can be reused on subsequent projects. This can reduce material requirements, waste and the environmental impact associated with temporary works. Ivor King maintains more than 3,000 tonnes of U and Z sheet piles in stock for hire and sale.

How are temporary sheet piles installed? caret-down

The installation method depends on the ground conditions, site constraints, required pile depth and surrounding environment. Sheet piles can be installed using vibratory excavator-mounted equipment (Movax), Telescopic Leader Rigs or GIKEN silent piling hydraulic presses. The appropriate method is considered as part of the design and planning process.

Can temporary piling be carried out where noise and vibration are a concern? caret-down

Yes. Where conventional piling methods are unsuitable because of sensitive structures, neighbouring properties or other environmental constraints, silent and vibration-free pressing systems such as GIKEN can be considered. These systems can be particularly useful in built-up or sensitive locations.

What information is needed to design temporary sheet piling? caret-down

Useful information includes the proposed excavation depth and layout, ground investigation information, water levels, surrounding structures and services, anticipated loads, site access and the construction programme. Early involvement allows the piling solution and installation method to be considered alongside the wider temporary and permanent works design.

col-temporary-sheet-pile-walls

Sheet Pile Retaining Walls

The quick and easy solution that eliminates the need for temporary earthworks support.

Sheet Pile Basement

Sheet Pile Basements

Maximise your basement footprint with a cost effective watertight construction solution.

Sheet Pile Cofferdam

Cofferdams

Allows excavation and construction in otherwise poor working environments

Temp Wall

Temporary Sheet Pile Walls

 

Allowing earthworks to take place, sheet piles can be re-used on project completion

Steel Bearing Piles

Steel Bearing Pile Foundations

Providing excellent load and resistance and high strength in compression and tension

Tied Wall Anchorage System

Tied Walls & Anchorage Systems

Sheet pile walls can be strengthened using anchorage systems to ensure the stability of retaining structures

Piling work

Inland Waterways & Marine Piling Solutions

Flood defences and water retention systems, including rivers, canals, harbour and dock wall stabilisations, marinas and reservoirs

Sheet Pile Hire & Sales Our dedicated hire and sales division is on hand to support all your temporary and permanent sheet pile needs

We are able to supply a wide variety of size, weight and grade of steel in both new mill certified piles and excellent quality used stock at competitive rates
piling solutions
Share This Article
facebook twitter linkedin